How we work
Audit, plan, implementation, handover
Four stages. You can stop between any two and pay only for what is finished - and roughly one client in three does exactly that.
Stage 1. Audit
Five working days of reading and talking. We change nothing, not even the obvious, and that is not politeness: anything fixed on day two becomes part of the picture we are trying to capture, and afterwards nobody can tell what was originally there.
Half the time goes on interviews - forty minutes with everyone who deploys anything by hand, plus a separate conversation with whoever gets woken up. People describe the parts that exist in no repository: the step always done twice, the check habitually skipped and why, the component everyone treats as cursed.
The other half produces numbers. We build the same commit twice and compare checksums. We bring up an environment from the written procedure, if one exists, and count the step at which it starts lying.
Stage 2. Plan
Three days, resulting in six to ten pages that state, for every piece of work: what we do, in what order, how long it takes, what stops working while it happens and who on your side is needed that day.
One section lists what we decided not to touch. It is almost always longer than people expect, and it is the part worth reading closely, because it says which risks you are choosing to live with. Once signed, the plan is the scope, and we do not amend it mid-flight - only by a separate agreement.
Stage 3. Implementation
Two to six weeks, depending on what the audit found. Two rules are not up for discussion.
One change at a time. Otherwise, a week later nobody knows which of four edits produced the result and which quietly broke something. Each change goes through a dry run that shows the difference before it is applied, and lands in a journal with an author and a reason.
Your engineer works with us. Not attends calls - works: they make about half the changes and we review them. This lengthens the project by roughly a quarter and is the only reason we know of that things still work six months later.
Stage 4. Handover
Two days, and the test is strict: somebody from the team who took no part in the implementation follows our document, brings up the environment from nothing and restores the data from a copy. We sit next to them and stay quiet. If they get stuck, the document is at fault, and we fix the document rather than explaining out loud.
Thirty days of written answers are included after handover. We answer questions but do not do the work: if those thirty days show the team cannot maintain something, we chose the wrong solution, and that is our mistake.
What this order does not include
- Daily calls. One written report at the end of each week, containing what was done, the numbers, and what did not work.
- Access to your passwords. Your side issues access with your own tools, and we ask you never to send credentials by email.
- Work that goes around your engineer, even when they are busy and ask us to «just do it and show me later».
How this looked on two real projects: the release case and the restore case. Prices per stage are on the services page.